Saint John has had a market ever since the City Charter of 1785 established such an entity. The first few buildings used for the purpose were in the vicinity of Market Slip at the foot of King Street. The earliest market structure in this location also served as Saint John’s City Hall and Courthouse. However, by the late 1820s both City Council and the Court had been relocated. Council minutes from the 1830s indicate that by this time the market building was in significant disrepair. The building survived the major fire of January 1837, but plans were already underway to build a new and more efficient market building.
The devastating fire of January 14, 1837, ravaged the south side of Market Slip and Market Square, destroying or damaging a significant portion of the surrounding area. In the aftermath, the Corporation of the City of Saint John moved quickly to address the question of a permanent market facility. At a meeting of Common Council on January 27th, a committee appointed to prepare plans and specifications for a new market house presented its recommendations. The committee submitted plans and specifications and recommended that tenders be sought for construction in wood and stone as well as brick, with an initial estimate of £601 14s for the proposed building.
The scale of the proposed undertaking quickly expanded. At the same meeting, Council ordered that an earlier decision to construct a building measuring ninety feet square be rescinded and that the new structure instead measure 100 feet by 90 feet. Tenders were to be invited for a brick building, with the work scheduled for completion by September 1st, 1838. The walls were to be erected by September 1, 1837, while the building was to be enclosed and covered by November so that the unfinished structure would be protected from the elements over the winter. Payment to the successful contractor was to be divided into stages, with one quarter due upon execution of the contract, another upon completion of the basement walls, another when the building was enclosed, and the remainder when the entire project was completed. Council also required the contractor to provide adequate security for the performance of the work.
Before construction could begin, however, the Corporation had to solve the rather practical problem of what to do with the butchers who occupied the existing market. The new building could not be constructed while the old market continued to operate normally, and Council therefore instructed its committee to arrange temporary accommodation. On January 28, tenders were advertised for the erection of a temporary butchers' market on King's Square. The proposed building was to measure 50 feet by 25 feet and was intended specifically to house the licensed butchers while the new market house was being constructed in Market Square. Contractors were required to provide all materials, and the temporary structure was to be completed by April 15, 1837.
The temporary market was completed within the following months. At its June 10th meeting, Council received a report from the committee responsible for overseeing the work stating that the building had been completed according to the plans and specifications, using “good material” and in a “sufficient and workmanlike manner.” The committee recommended that the contractor be paid £156 for the work. The temporary structure was subsequently enlarged in March 1838, when an additional thirty-eight and half feet was added to its length at a cost of £60. Its uses also expanded as by January 1840 space had been arranged within the building for a temporary weighing house, while part of the structure was being used to house a new fire engine. In its final form, the temporary market measured approximately 86 feet by 25 feet. Thus, what had initially been conceived as a short-term solution remained a useful municipal facility for several years.
With the butchers temporarily accommodated, attention returned to the construction of the permanent market in Market Square. In January 1837, the Corporation had advertised for tenders for a new market house measuring 100 feet by 90 feet and rising two stories above a basement. The building was to be constructed of brick and stone with a roof covered with slate. The specifications reveal an impressive level of detail and provide a sense of the ambitions attached to the project. The basement was to contain substantial stonework and masonry, while the exterior walls were to be constructed of high-quality stock brick. The first story was to contain the principal butchers' market, with sixteen brick pillars supporting brick arches. Above it, the second story was to contain additional rooms and market space.
The plans called for substantial foundations, carefully finished cut-stone elements, brick arches, plastered rooms, elaborate cornices, numerous large windows, and substantial timber framing. The roof was to be covered with Westmorland slate, while copper and lead were specified for various portions of the roof and chimneys. Windows were to be glazed with crown glass, and the doors were to be painted in imitation oak. The Corporation required the finished work to be “plain” but “substantial and durable,” suggesting that although the building was fundamentally utilitarian, considerable attention was given to its appearance.
Construction proceeded through 1837 and into the following year, although the work was not without incident. On May 26, 1837, part of the platform attached to the existing market house collapsed, injuring several people who were standing nearby. According to a report published in The Courier the following day, the accident resulted from excavations being undertaken for the foundations of the new market house. Despite this setback, the project was eventually completed, producing a substantial new structure in the centre of Market Square. The building brought together several municipal and commercial functions, housing the butchers' market, a bonded warehouse, and civic offices. Its construction represented a considerable investment by the Corporation, costing approximately £10,000.
The new market house would, however, have a relatively short existence. On November 15, 1841, another major fire broke out on the South Market Wharf. The blaze spread rapidly, destroying buildings along the South Market Wharf, Ward Street, Water Street, and the south side of Market Square, before extending along the west side of Prince William Street. Among the most significant losses was the recently constructed market house, which was completely destroyed. The Corporation reportedly held only £3,000 in insurance against the building's approximately £10,000 construction cost. Once again, the city was left without its principal market facility, necessitating renewed consideration of how best to accommodate its butchers, merchants, and other market vendors.[1]
[1] All information for this post comes from an unpublished manuscript To Us a Legacy by Gerald F. Wallace (1978) in the archive of the New Brunswick Museum.
Artwork by Marking the Market volunteer Keith Colwell